ENHANCED LANDFORCE TRAINING FACILITY - WATSONIA
            Completed: 2011
        
        
            
                GROSS FLOOR AREA
                5,000m2
            
            
                LEVELS
                5
            
            
                PROJECT COST
                $6.8M
            
         
        
            Simpson Army Barracks, Watsonia.
5 storey military grade Enhanced Landforce Trainining Facilty for Australian Defence Force.
3, 4 and 5 day cycles were achieved for both vertical and horizontal concrete elements.
Project was completed 2011.
SCOPE OF WORKS: 
• FORMWORK DESIGN, SUPPLY AND INSTALLATION
• REINFORCEMENT SUPPLY AND PLACEMENT
• CONCRETE SUPPLY AND PLACEMENT
• CONCRETE PUMPING