THE HUB - RICHMOND
Completed: February 2015
GROSS FLOOR AREA
19,000m2
LEVELS
11
PROJECT COST
$43M
4-16 Garfield Street, Richmond.
9 storey residential building plus 2 basements containing 170 apartments.
3, 4 and 5 day cycles were achieved for both vertical and horizontal concrete elements.
Project commenced in January 2014 and was completed by February 2015.
12 months completion 9 level structure with 2 basements.
SCOPE OF WORKS:
• PRECAST CORE JUMP-FORM SYSTEM INSTALLATION AND MANNING CYCLES
• PERIMETER SAFETY SCREENS INSTALLATION AND MANNING CYCLES
• FORMWORK DESIGN, SUPPLY AND INSTALLATION
• PRECAST INSTALLATION