INFINITY 8 & 88 - MELBOURNE
Completed: 2013
GROSS FLOOR AREA
13,000m2
LEVEL STAGES
10 & 20
PROJECT COST
$44M
243-263 Franklin Street, Melbourne.
Stage 1: 10 storey residential and commercial building containing 90 apartments and 3 retail outlets.
Stage 2: 20 strorey residential and commercial building containing 169 apartments and 2 retail outlets.
3, 4 and 5 day cycles were achieved for both vertical and horizontal concrete elements.
Project was completed 2013.
SCOPE OF WORKS:
• PRECAST CORE JUMP-FORM SYSTEM INSTALLATION AND MANNING CYCLES
• PERIMETER SAFETY SCREENS INSTALLATION AND MANNING CYCLES
• FORMWORK DESIGN, SUPPLY AND INSTALLATION
• PRECAST INSTALLATION
• REINFORCEMENT PLACEMENT
• POST TENSION DESIGN AND CONSTRUCT
• PRECAST INSTALLATION