NO. 8 LYGON ST - BRUNSWICK

Completed: SEPTEMBER 2017

GROSS FLOOR AREA 22,000m2

LEVELS 8

PROJECT COST $50m

8 Lygon Street, Brunswick East.
2 basement and 9 storey residential development on a large footprint containing 192 apartments.
3, 4 and 5 day cycles were achieved for both vertical and horizontal concrete elements.

 Project commenced in February 2017 and was completed by September 2017.
 7 months completion 22,000m2 gross floor area.

SCOPE OF WORKS: 
• PRECAST CORE JUMP-FORM SYSTEM DESIGN, SUPPLY, INSTALLATION AND MANNING CYCLES
• PERIMETER SAFETY SCREENS DESIGN, SUPPLY, INSTALLATION AND MANNING CYCLES
• FORMWORK DESIGN, SUPPLY AND INSTALLATION
• REINFORCEMENT SUPPLY AND PLACEMENT
• POST TENSION DESIGN AND CONSTRUCT
• PRECAST INSTALLATION