PALLADIUM TOWER - SOUTHBANK
            Current: OCTOBER 2019 – 
        
        
            
                GROSS FLOOR AREA
                39,000m2
            
            
                LEVELS
                52
            
            
                PROJECT COST
                $100M
            
         
        
            245 City Road, Southbank.
The Palladium Tower will house commercial offices, small supermarket and 279 apartments.
3, 4 and 5 day cycles were achieved for both vertical and horizontal concrete elements.
Project commenced in October 2019 and expected completion by October 2020. 
12 months completion  52 level structure.
SCOPE OF WORKS: 
• CORE JUMP-FORM SYSTEM DESIGN, SUPPLY, INSTALLATION AND MANNING CYCLES
• PERIMETER SAFETY SCREENS DESIGN, SUPPLY, INSTALLATION AND MANNING CYCLES
• FORMWORK DESIGN, SUPPLY AND INSTALLATION
• CONCRETE PLACEMENT
• REINFORCEMENT INSTALLATION
• POST TENSION SUPPLY AND INSTALLATION
• PRECAST INSTALLATION