INK HOTEL - SOUTHBANK
Completed: MAY 2018
GROSS FLOOR AREA
6,000m2
LEVELS
16
PROJECT COST
$30m
167 City Road, Southbank.
16 storey modern hotel development.
3, 4 and 5 day cycles were achieved for both vertical and horizontal concrete elements.
Project commenced in November 2017 and was completed by May 2018.
6 months completion 16 level structure.
SCOPE OF WORKS:
• PRECAST CORE JUMP-FORM SYSTEM DESIGN, SUPPLY, INSTALLATION AND MANNING CYCLES
• PERIMETER SAFETY SCREENS DESIGN, SUPPLY, INSTALLATION AND MANNING CYCLES
• FORMWORK DESIGN, SUPPLY AND INSTALLATION
• CONCRETE SUPPLY AND PLACEMENT
• CONCRETE PUMPING
• REINFORCEMENT SUPPLY AND PLACEMENT
• POST TENSION DESIGN AND CONSTRUCT
• PRECAST INSTALLATION
• SPEEDWALL INSTALLATION